Once a Camcode Project Manager has reviewed an Order via Recon or Import and fixed any errors that occur in the file, the PM can then submit the order for production. This is done by following steps.
Step 1: The Project Manager must click the Submit Order button as highlighted below.
Step 2: The Project Manager must choose Cleveland Production if the tags are to be made in the Camcode Cleveland office.
Step 3: The Camcode Project Manager must choose a kitting option. The Project Manager can either choose to kit by:
- By NSN
- By Location
- By NSN and Location
Once this is selected the Project Manager has completed all their steps and the order is about to be produced and shipped asap for installation.